Within the framework of preparation for the fall-winter period of 2023-2024, inspection of the 27 MW gas turbine unit of Tashkent CHPP is carried out

The tasks set within the framework of the repair are fulfilled by the specialists of the enterprise and “Uzenergosozlash” LLC.

To date, the blades of the third stage of the gas turbine rotor as well as gas burners of the gas turbine have been replaced. The stator part has also been repaired.

At the moment, work is underway to install the generator rotor.
The repair works will continue until September 30. The purpose of repair works is to ensure stable supply of heat and electric energy to consumers.